Facilities & Capital Management Projects

  Project Title Project Costs Focus Rebates Annual Savings Complete
  County Buildings:  Installed three cases of CFL’s.       X
  Lighting Analysis:  Courthouse and Social Services - Lighting engineer did an audit of these building and makes recommendations on where to save energy. $5,599.68     X
 

Lighting Analysis:  Juvenile, 210 River Drive, 212 River Drive, and 326 River Drive - Lighting engineer did an audit of these buildings and makes recommendations on where to save energy.

 $2,068.50     X
  (2012) Variable Frequency Drives:  Courthouse, Jail, and Social Services - replaced variable frequency drives. $16,684.27 $4,420.00   X
  (2011) Courthouse:  Replaced 4 light fixtures with LED retrofit fixtures. $235.00 $99.03   X
  (2008) Courthouse Boiler:  Boiler tune up. $1,461.16 $1,095.87   X
  Courthouse Envelope Study: $4,600.00     X
  Courthouse Lighting Retrofit:  Project to implement recommendations of the lighting analysis. $94,711.63 $21,016.00 $27,300.00 X
  (2008) Courthouse Stairwell Lighting:  Installed auto dimming lights in stairwells. $4,835.60 $720.00   X
  (2015) Courthouse Underground Parking Lighting:  Installed LED canopy lights. $5,750.00 $1,100.00   X
  (2013) Jail HVAC Project:  Install A/C units in jail kitchen. $15,083.28 $400.00   X
  (2014) Jail Chiller Project:  Replaced chiller. $34,625.92 $876.00   X
  (2010) Jail Laundry Project:  Replaced clothes dryer. $4,599.00 $572.00   X
  (2011) Jail Walk-in-Cooler Project:  Replaced two motors with more efficient equipment. $239.40 $120.00   X
  (2009) Juvenile Facility:  Boiler tune-up. $1,075.80 $300.00   X
  (2015) Juvenile Facility Boiler Project:     Replaced three boilers. $51,371.50 $7,727.50   X
  Juvenile Facility Lighting Retrofit:  Project to implement recommendations of the lighting analysis. $7,859.60 $569.50   X
  (2015) Library Boiler Project:  Replaced boiler. $68,005.05 $9,900.00   X
  Library Lighting Analysis:  Lighting engineer did an audit of our Library and makes recommendations of the lighting ananlysis. $2,677.00     X
  Library Lighting Retrofit:  Project to implement recommendations of the lighting analysis. $47,671.59 $5,111.50   X
  (2008) Library 3rd Floor Lighting:  Removed metal halide light fixtures and installed motion sensors and timers. $2,601.16 $1,120.00   X
  210 River Drive Lighting Retrofit:  Project to implement recommendations of the lighting analysis. $27,245.14     X
  212 River Drive:  Removed half of the light fixtures in the hallway. 0   $700.00 X
  212 & 326 River Drive Lighting Retrofit:  Project to implement recommendations of the lighting analysis. $8,482.63     X
  (2012) Social Services Chiller Project:  Replaced chiller. $54,000.00 $2,664.75   X
  Social Services Lighting Retrofit:  Project to implement recommendations of the lighting analysis. $31,137.98 $6,060.00   X
  Social Services Window Project:  Replacement of all existing windows with more energy efficient glass and framework. We also added insulation while the windows were removed and doubled the r value (insulation) in the lobby area. $187,219.47     X
  (2013) UW Marathon County Chiller Project:    Replaced North hall chiller. $183,504.00 $3,604.12   X
  (2008) 1308 West Street Maintenance Building Lighting Project:  Removed metal halide light fixtures and installed motion sensors and timers. $2,394.30 $1,110.00   X

 

Marathon County Parks, Recreation, and Forestry Department Energy Efficient Lighting Projects

Project Title Project Costs Focus Rebates Annual Savings Complete
East Gate Hall: Replacement of metal halide fixtures with T8 fluorescent fixtures. $3,267.00 $1,180.00 $600.00 X
Marathon Park: Replacement of (8) cobra head 400 watt HPS with 228 watt LED. $4,160.00 $320.00

$984.00/year   4.2 year payback

X
Marathon Park: Replacement of (7) 250 watt HPS wall pack fixtures with 52 watt LED. $2,009.00 $175.00 $854/year   2.3 year payback X
Marathon Park: Replacement of (3) 150 watt HPS wall pack fixtures with 26 watt LED. $600.00 $75.00 $222/year   2.7 year payback X
(2015) Marathon Park:  Replacement of HID to LED lights along roadway.   $660.00   X
Marathon Park Multi-Purpose Buildings: Replacement of light fixtures and addition of sensors throughout buildings. Re-designed lighting layout throughout buildings. $27,578.74 $14,578.01 $3,375/year
3.5 year payback period
X
Park Operations Building: Replacement of light fixtures and addition of sensors throughout buildings. $14,903.00 $6,630.00 $1,950/year
4 year payback period
X

 

Marathon County Highway Department

Project Title Project Costs Focus Rebates Annual Savings Complete
Abbotsford Shop Light Replacement: Replaced 23 highbay 400watt metal halide light with 23 250watt T5HO fluorescent fixtures with occupancy sensors on each fixture. $6,191.33 $2,990.00 $783.38 X
Hatley Shop Light Replacement: Replaced 28 highbay 400watt metal halide with 28 250watt T5HO fluorescent fixtures with occupancy sensors on each fixture. $7,421.88 $3,640.00 $953.68 X
Stratford Storage Light Replacement: Replaced 10 highbay 400watt metal halide with 10 250watt T5HO fluorescent fixtures with 6 occupancy sensors controlling lights. $3,376.79 $1,300.00 $340.60  X

 

Airport Projects

Project Title Project Costs Focus Rebates Annual Savings Complete
Air Freight Building: 5 400W MH lights to new T-8s. $695.15 $450.00   X
FBO hangars: 49 400W MH lights to new T-8s. $6,812.47 $4,410.00   X
Terminal Restaurant: Replaced inefficient watercooled ice maker with new energy efficient electric compressor model. $3,376.79 $300.00 $3,000.00 X
We also completed boiler tune-ups for the terminal under the program, but don’t have any hard numbers because of different number of heating days, etc.

 

Marathon County is committed to being an “Environmentally Responsibile County Government”, which includes policies and programs that conserve energy, and reduce fuel/utility/resource consumption.

These projects are a collaboration of Focus on Energy and Wisconsin Public Service and Marathon County.

   Focus on Energy   Wisconsin Public Service