County Road N Construction - Towns of Easton and Plover SCHEDULE UPDATE

County Road N in the Towns of Easton and Plover between Forestville Road and Pleasant Drive will be under construction July 1st through late July/early August.  The project was originally scheduled to begin June 27th, the start date has been delayed to July 1st due to some delays with construction equipment.

During the week of July 5th, crews will use specialized equipment to recycle the roadway into a Cold In-Place recycled pavement foundation.  This foundation will require approximately 7-14 days to cure before the final pavement can be placed.  Crews plan to place the final pavement surface beginning July 18th. 

Gravel shoulders and pavement marking are planned to be placed at the end of July. 

No Detour Route will be posted for this project.  Access for local residents and businesses will remain at all times during construction.  Drivers should expect delays and should use alternate routes when possible.  