County Road X Construction - Town of Wausau SCHEDULE UPDATE

County Road X in the Town of Wausau between County Roads N and Z will be under construction beginning July 5th.  The project was originally scheduled for July 11th and was accelerated to a July 5th start date.  

Crews will process the existing pavement into a gravel surface the week of July 5th.  Paving operations are scheduled to begin the week of July 11th.  Gravel shoulders and pavement markings are scheduled to be placed at the end of July.  

Traffic is asked to detour around the project using County Road J.  Access will be maintained for residents and businesses.  The road will be rough at times, drivers should expect delays; please use alternate routes when possible.

(View Count: 3403) Actions: E-mail